Barnett Southern completed the clearing, grading, storm drainage, water quality trenches and base stone installation for the Midcoast Airport runway extension. Over 160,000 cubic yards of onsite dirt was moved and over 190,000 cubic yards of import dirt was placed on this project. The water quality trenches covered an approximate area of 6 acres and included approximately 30,000 tons of aggregate. This project was plagued by inclement weather and was in a low lying area so continual dewatering was utilized for the project duration.